Working With the Customer: Updates, Expectations and Saying No
the customer rarely fires you for bad news; they fire you for late news
Open the interactive lessonIn a forward-deployed role the code is half of it. The other half is a customer who has a boss, a budget, a calendar, and strong opinions about data they have never actually looked at. Interviewers probe this with behavioural-sounding questions inside the technical round: "the customer asks you to add something that was not in scope, what do you do?", "your estimate was wrong, how do you tell them?", "the customer insists the data is clean but you can see it is not."
Scenario used throughout: you are three weeks into building a tool for a retail chain's supply planners. Your sponsor is a regional operations director; day to day you work with a planning manager. Everything below is the sort of thing that happens in that setup.
Bad news early, and a weekly update that does not change shape
Bad news has a half-life. On day three, "the extraction rate is lower than I hoped" is a small, useful sentence. By week three, the same fact is a missed deadline, a confused sponsor and a trust problem. The work did not change; the delay in telling them did. My rule is that I say it the same day I am confident it is true, and I do not wait for a fix first. A customer can cope with "this is a problem, here is what I am doing about it"; they cannot cope with discovering it from someone else.
A good bad-news message has four parts, in this order: what happened, in one plain sentence; how it affects them, in their terms (a date, a number, a person's time); what I am doing about it; and what I need from them, if anything. No apology paragraph, no technical history. For example: "The warehouse export has duplicate rows for about one SKU in eight. It means my forecast numbers are off until I clean it. I am dedup'ing it now and will have corrected numbers Thursday. I need five minutes with Priya to confirm which duplicate is the real one."
The weekly update, in a fixed shape: done, next, risk, ask. The shape matters more than the prose because it trains the sponsor to read it in thirty seconds and to notice when a section is empty.
- Done: what is finished and observable, with a number if I have one. Not "worked on the model" but "forecast now covers 40 of 60 store clusters; the error on last month's data was, for example, about 12 percent."
- Next: what I will finish by next week, in at most three lines. This is a promise, so I keep it small.
- Risk: the one or two things that could make "next" slip, in plain words, with an honest likelihood. An update with no risk line is not good news, it is a sign nobody is thinking about risk.
- Ask: the specific thing I need from them, with a name and a date. Access, a decision, a person's afternoon. If the ask is empty I write "none this week" so the section is visibly checked.
The same structure every week also makes a bad week survivable. When a risk becomes a miss, the customer has already seen it in the risk line two weeks running; it is not a surprise, and surprise is the thing that damages relationships.
Who the real stakeholder is, and what a champion can and cannot do
Your daily contact is usually not the person who decides if you stay. The planning manager who answers your messages is your champion: someone who wants this to work, gives you access, and explains how things really operate. The regional director who signed off the project is the stakeholder (sometimes called the sponsor or economic buyer): the person whose number improves if you succeed and who can extend, shrink or end the engagement. They are often different people, and mixing them up is a classic mistake.
What the champion can do: unblock data, introduce you to the right people, tell you what the sponsor actually cares about. What the champion cannot do: approve a scope change, accept a result as "good enough," or protect the project if the sponsor loses interest. A champion who says "yes, just add that" is being helpful, but it is not a decision until the person who owns the budget agrees.
How I find out who is who without being awkward. Early on I ask, in plain words: "When this is finished, whose number changes? Who will be asked in six months whether it worked?" The answer names the stakeholder. Then I ask the champion how that person likes to be updated, and I make sure the weekly update reaches them, either directly or through the champion with the champion's agreement. I never go around the champion; that burns the one person who makes my days work.
The failure to avoid: spending three weeks delighting the champion with features while the sponsor, who sees only a monthly summary, concludes nothing visible has changed. The champion's enthusiasm is a resource; the sponsor's number is the goal. Both need regular, different kinds of attention: the champion needs working sessions, the sponsor needs the outcome in their own units.
A practical rhythm: weekly working session with the champion, weekly written update that both read, and a short sponsor check-in every two or three weeks that shows one number moving. If the sponsor does not want check-ins, that itself is information I pass to the champion gently.
Scope creep, "just add AI", and saying no with an alternative
Scope creep rarely arrives as a big demand. It arrives as "while you are in there, could you also..." from someone friendly, in the middle of a meeting. If I say yes on the spot I have changed the plan without anyone who owns the plan deciding, and every other deadline silently moves.
My response has three beats: acknowledge, size, trade. "That is a sensible idea. I think it is about three days of work, which would push the planned supplier view to the week after. Do you want me to swap it in, or keep the current order and put this next?" This is not refusing. It puts the cost on the table and hands the choice to the person who owns priorities. If it is a sponsor-level change, I write it in the weekly update's ask section so it is a recorded decision.
"Just add AI." Sometimes the sponsor has been told by their own leadership to include AI somewhere. I do not argue about the word. I ask what decision or task they want it to help with, and what the current process costs. Then one of three things happens. The task is genuinely suited to a model, a good addition, and I scope it like any slice. Or a simple rule or lookup would do the same job more reliably, and I say so with the reason: "a plain threshold gets you the same answer, you can read it, and it will not change behaviour next month." Or the thing is wanted for appearances, and I can offer a small, honest version that I can measure, rather than a large vague one that I cannot.
How to say no with an alternative. A bare no sounds like obstruction. The structure I use: what I cannot do and why, in their terms; what I can do instead; what it would take to do the original. For example, asked to deliver live store-level predictions by next week: "I cannot make store-level predictions trustworthy by then, because half the stores have under three months of history. I can give you cluster-level numbers next week, which are solid, and store-level for the stores with enough history. Store-level for all of them needs about six more weeks of data or a decision to borrow history from similar stores, which I would want you to approve."
What I never do: say yes to keep the peace and quietly absorb the cost with late nights. It looks generous and it removes the customer's ability to make a real trade-off. It also resets expectations of what normal pace is.
When the customer is wrong about the data. The planning manager says, firmly, "our sales data is clean." You have found 8 percent of rows with negative quantities. Do not argue and do not say "you are wrong." Show, don't tell: pull ten concrete rows, bring them to a working session, and ask "help me understand what these mean; I am sure there is a reason." Sometimes they are right and there is a convention you did not know, such as negatives representing returns. Sometimes they are wrong, and having seen the rows themselves, they say so before you have to. Either way the customer keeps their dignity and you get the truth. Then write down the agreed meaning in a shared note so the next person does not rediscover it.
Follow-ups they will ask
"The sponsor and the champion disagree on what you should build. Whose view wins?" The sponsor's, because they own the outcome, but I would not decide that silently or by going around the champion. I would put both views side by side in plain words, name what each is trying to achieve, and ask the two of them to agree in one conversation I help set up. Often the disagreement is about order, not content, and a slice plan resolves it.
"The customer demands a date you do not believe." I give the date I believe, with the reason, and add what would have to be true to hit theirs: less scope, more access, an extra person from their side. I do not agree to a date I expect to miss because the miss will land on the relationship, not the schedule. A customer who hears "here are three ways to get there faster, with their costs" usually picks one.
"You made a mistake that affected their numbers. What do you do?" I tell them as soon as I am sure, using the four-part bad-news shape: what happened, what it affected, what I have done, what I need. I give the corrected numbers and a note on how I will stop it recurring. Owning it quickly, without long excuses, typically strengthens trust, because the customer learns I will surface problems rather than hide them.
"The champion goes quiet for two weeks." I assume something changed on their side, not that they stopped caring. I ask a direct, low-pressure question, "is this still a priority for your team? I want to be sure I am building for the right thing," and I check with the sponsor that the project is still wanted. Silence from a champion is an early warning that the sponsor's priorities moved.
"How do you say no to the executive who asked for the AI feature?" I do not say no to the person; I say yes to their goal. "You want fewer stock-outs. Here is the smallest thing that moves that number, and here is where a model would genuinely add something later." If they still insist, I scope the smallest honest version, give it a measurable success line, and let the number decide.
How to say it in the interview
"I treat the customer relationship as part of the system I am building. Bad news travels best early and in a fixed format, scope changes get a written trade-off instead of a quiet yes, and when I say no I always bring an alternative, because a no with nothing attached just sounds like an obstacle."
Checklist
- Told the customer bad news the same day I was sure of it, not after I had a fix
- Used a fixed update shape of done, next, risk, ask, with the risk line never empty
- Separated the champion from the real stakeholder, and gave each a different kind of attention
- Answered scope requests with acknowledge, size, trade instead of a quiet yes or a flat no
- Asked what decision 'AI' was meant to help with before agreeing or refusing
- Showed concrete rows when the customer was wrong about their data, instead of arguing